Manufacturing Cycle Time Analysis and Scheduling to Optimize Its Duration
Апстракт
This paper reports the results of investigations on manufacturing cycle times for special-purpose products. The company performs serial production characterized by complex and diverse technologies, alternative solutions and combined modes of workpiece movement in the manufacturing process. Because of various approaches to this problem, an analysis of previous investigations has been carried out, and a theoretical base is provided for the technological cycle and factors affecting the manufacturing cycle time. The technological and production documentation of the company has been analysed to establish the technological and real manufacturing cycle times, total losses and flow coefficients. This paper describes the original approach to production cycle scheduling on the grounds of investigations of manufacturing capacity utilization levels and causes of loss, in order to measure their effects and to reduce the flow coefficient to an optimum level. The results are a segment of complex stud...ies on the production cycle management of complex products, accomplished in the company in the period from 2010 to 2012.
Кључне речи:
serial production / production losses / material flow / manufacturing cycle / manufacturing capacity utilization levelИзвор:
Strojniski Vestnik-Journal of Mechanical Engineering, 2014, 60, 7-8, 512-524Издавач:
- Assoc Mechanical Engineers Technicians Slovenia, Ljubljana
DOI: 10.5545/sv-jme.2013.1523
ISSN: 0039-2480
WoS: 000339229200007
Scopus: 2-s2.0-84904860195
Колекције
Институција/група
Mašinski fakultetTY - JOUR AU - Jovanović, Jelena R. AU - Milanović, Dragan AU - Djukić, Radisav D. PY - 2014 UR - https://machinery.mas.bg.ac.rs/handle/123456789/1882 AB - This paper reports the results of investigations on manufacturing cycle times for special-purpose products. The company performs serial production characterized by complex and diverse technologies, alternative solutions and combined modes of workpiece movement in the manufacturing process. Because of various approaches to this problem, an analysis of previous investigations has been carried out, and a theoretical base is provided for the technological cycle and factors affecting the manufacturing cycle time. The technological and production documentation of the company has been analysed to establish the technological and real manufacturing cycle times, total losses and flow coefficients. This paper describes the original approach to production cycle scheduling on the grounds of investigations of manufacturing capacity utilization levels and causes of loss, in order to measure their effects and to reduce the flow coefficient to an optimum level. The results are a segment of complex studies on the production cycle management of complex products, accomplished in the company in the period from 2010 to 2012. PB - Assoc Mechanical Engineers Technicians Slovenia, Ljubljana T2 - Strojniski Vestnik-Journal of Mechanical Engineering T1 - Manufacturing Cycle Time Analysis and Scheduling to Optimize Its Duration EP - 524 IS - 7-8 SP - 512 VL - 60 DO - 10.5545/sv-jme.2013.1523 ER -
@article{ author = "Jovanović, Jelena R. and Milanović, Dragan and Djukić, Radisav D.", year = "2014", abstract = "This paper reports the results of investigations on manufacturing cycle times for special-purpose products. The company performs serial production characterized by complex and diverse technologies, alternative solutions and combined modes of workpiece movement in the manufacturing process. Because of various approaches to this problem, an analysis of previous investigations has been carried out, and a theoretical base is provided for the technological cycle and factors affecting the manufacturing cycle time. The technological and production documentation of the company has been analysed to establish the technological and real manufacturing cycle times, total losses and flow coefficients. This paper describes the original approach to production cycle scheduling on the grounds of investigations of manufacturing capacity utilization levels and causes of loss, in order to measure their effects and to reduce the flow coefficient to an optimum level. The results are a segment of complex studies on the production cycle management of complex products, accomplished in the company in the period from 2010 to 2012.", publisher = "Assoc Mechanical Engineers Technicians Slovenia, Ljubljana", journal = "Strojniski Vestnik-Journal of Mechanical Engineering", title = "Manufacturing Cycle Time Analysis and Scheduling to Optimize Its Duration", pages = "524-512", number = "7-8", volume = "60", doi = "10.5545/sv-jme.2013.1523" }
Jovanović, J. R., Milanović, D.,& Djukić, R. D.. (2014). Manufacturing Cycle Time Analysis and Scheduling to Optimize Its Duration. in Strojniski Vestnik-Journal of Mechanical Engineering Assoc Mechanical Engineers Technicians Slovenia, Ljubljana., 60(7-8), 512-524. https://doi.org/10.5545/sv-jme.2013.1523
Jovanović JR, Milanović D, Djukić RD. Manufacturing Cycle Time Analysis and Scheduling to Optimize Its Duration. in Strojniski Vestnik-Journal of Mechanical Engineering. 2014;60(7-8):512-524. doi:10.5545/sv-jme.2013.1523 .
Jovanović, Jelena R., Milanović, Dragan, Djukić, Radisav D., "Manufacturing Cycle Time Analysis and Scheduling to Optimize Its Duration" in Strojniski Vestnik-Journal of Mechanical Engineering, 60, no. 7-8 (2014):512-524, https://doi.org/10.5545/sv-jme.2013.1523 . .